By Nick, Active Termite Control, Earlwood. NSW EPA pesticide licence 5074559 (timber pest control). Job: a new home in Sydney.

The short version: An owner building a new home rang me on a Friday. The slab pour was coming up, and the part of the termite barrier that has to go in before the concrete needed doing. I came out that weekend and did the pre-pour stage, so the pour wasn't delayed.

The problem

On a slab-on-ground build, part of the termite protection has to be in before the concrete is poured. Pipes and services come up through the slab, and the gaps around them are one of the common ways termites get into a house. Once the concrete is down you can't get to those gaps any more, so if that part of the barrier isn't in, the pour has to wait.

New-build termite protection is set out in Australian Standard AS 3660.1 and the National Construction Code (Part 3.4).

What I did

I came out on the weekend and did the pre-pour stage of the barrier, installed to AS 3660.1. With it in, the pour went ahead without a delay.

What the pre-pour stage is

  • Collars around every pipe and service penetration, fitted before the pour, so termites can't come up through the gaps around the pipes.
  • A soil treatment at those same penetrations, which closes the gap around the pipes that a collar alone can't fully seal.

What comes after the pour

The barrier goes in in two stages. After the pour, the sheeting is bonded to the slab edge while the edge is still exposed. That has to happen before the edge disappears under cladding, render or landscaping, because once it's covered the option is gone for good.

When the barrier is finished, the owner or builder gets the installation certificate, and a durable notice goes in the meter box, so anyone who works on the house later can see what's installed.

If you're building

  1. Raise termite protection early, while you're still planning the slab, not the week before the pour. Every build's timing is different.
  2. Tell me where the build is up to, so the collars go in before the pour and the sheeting goes on after it, while the slab edge is still exposed.
  3. Keep the slab edge visible once the house is finished. See the 75 mm inspection zone.
  4. Book a termite inspection every year. Later work like paths, garden beds or an extension can bridge a barrier, and the yearly inspection is what catches it.

More on the rules in AS 3660.1 for new homes and the NCC for builders, and on the service at pre-construction termite barriers.

Building in Sydney?

Call me on 0405 790 927 and tell me where the build is up to.

Call 0405 790 927

More real jobs: all case studies.

Need help? Call Nick
directly, 7 days

Sydney's termite specialist. Inspections and treatments, 7 days. Call 0405 790 927.
Call Now
Call 0405 790 927